PSC CAR SHREDDER RELOCATION 

St. Louis, MO

PSC Metals purchased an existing shredder located in Alton, IL to increase the capacity of their St. Louis facility. L. Keeley’s Industrial Team was approached for their ability to offer a turn-key solution and for our experience installing that exact same shredder in Alton, IL seven years prior. L. Keeley relocated the shredder to PSC’s St. Louis Facility. Foundations and machinery installation dates were staggered to maintain an efficient schedule fully utilizing our 30 plus manpower crew.

 

One challenge the team faced during construction was that the pipe pile received from the manufacturer did not meet design requirements. L. Keeley was able to fabricate a suitable collar around the manufacturers welds to meet the necessary strength requirements. L. Keeley’s ability to find and implement a solution saved the client several weeks that it would have taken to re-procure new pipe pile. L. Keeley self-performed 80% of the project including; site civil, pile driving, concrete foundations, steel erection, millwright installation of equipment, flatwork, and carpentry work.

bottom of page